隧道建设(中英文) ›› 2014, Vol. 34 ›› Issue (1): 1-5.DOI: 10.3973/j.issn.1672-741X.2014.01.001

• 专家论谈 •    下一篇

台湾海峡隧道工程规划方案若干关键性问题的思考

孙钧1, 2   

  1. (1. 同济大学隧道与地下工程研究所, 上海 200092; 2. 上海市城建集团院士工作研究室, 上海 200122)
  • 收稿日期:2013-12-02 出版日期:2014-01-20 发布日期:2014-01-21
  • 作者简介:孙钧(1926— ),男,江苏苏州人,1949年解放前夕毕业于上海国立交通大学土木工程系结构工程专业。国内外隧道与地下工程知名学者、专家,同济大学荣誉、一级、终身教授,中国科学院(技术科学部)资深院士,前国际岩石力学学会副主席暨中国国家小组主席,中国岩石力学与工程学会名誉理事长(前理事长),中国土木工程学会顾问、名誉理事(前副理事长),中国土木工程学会、中国公路学会、上海市土木工程学会等学会隧道与地下工程分会前副理事长、理事长,福建省交通协会海峡两岸通道桥隧工程学术委员会主任委员。

Views on Key Technical Issues of Construction of Taiwan Strait Tunnel

SUN Jun 1, 2   

  1. (1. Tunnel and Underground Work Research Institute of Tongji University, Shanghai 200092, China; 2. Academician’s Research Studio of Shanghai Urban Corporation, Shanghai 200122, China)
  • Received:2013-12-02 Online:2014-01-20 Published:2014-01-21

摘要:

首先对台湾海峡隧道的若干技术关键问题作了简要归纳,包括地质地貌、线位选择、过海交通方式、耐久性问题、施工方法、加建中间服务隧道的必要性及主要功能等。简要分析了修建隧道过海的技术优势和存在的问题,指出对台海大通道桥、隧方案的比选和优化,日后定将是前期方案和工程可行性设计中的重中之重,应从长计议。重点对隧道越海施工方案和工期的设想进行了阐述,推荐采用第1方案(中间服务隧道5.5先行,主洞大型TBM8.0 m 和后面的车架先拆卸成块后从服务隧道和平洞进入主隧道内,经洞内组装后再开挖掘进),第2方案作为备选(先用5.5 m TBM开挖经横洞时仍需拆卸,待进入主隧道后再在洞内组装;主洞先形成5.5 m小洞后,随后再用钻爆法扩挖成型8.0 m)。按第1种方案对150 km的隧道工期进度进行了估算,含地勘在内的估算工期约为30年。

关键词: 台湾海峡隧道, 桥、隧方案比选, 施工方案, 工期

Abstract:

The key technological issues related to Taiwan Strait Tunnel, including geological and topographic conditions, alignment selection, seacrossing transportation modes, durability, construction methods, necessity to build service tunnel and the functions of service tunnel, are summarized. The advantages of and the problems in building the sea crossing tunnel are analyzed briefly. This paper points out that it is fundamental to make a proper final choice from the bridge option and the tunnel option. The construction scheme and construction schedule related to the tunnel solution are discussed. It is proposed that scheme 1, i.e., the 5.5 m service tunnel is driven first, then 8.0 m TBMs and their backup systems for the main tunnels are taken apart into several parts,from the first to through the service tunnel and the cross passage opening and are then assembled in the main tunnels before the main tunnels are driven by the TBMs, should be adopted, and that scheme 2, i.e., the 5.5 m service tunnel is driven first, then 5.5 m TBMs and their backup systems for the main tunnels are taken apart also into several parts only when it passing through the cross passage opening, delivered into the main tunnels and assembled to bore 5.5 m pilot tunnels at first, and thereafter are enlarged to 8.0 m main tunnel by drill and blast method, be adopted as standby. It is estimated that, in the case of scheme 1, the total construction period of the 150 kmlong Taiwan Strait Tunnel should be about 30 years.

Key words: Taiwan Strait Tunnel, comparative analysis on bridge solution and tunnel solution, construction scheme, construction schedule