内河中游沉管隧道管节浮运沉放水文窗口选择研究

韩建坤   

  1. (中铁隧道集团二处有限公司, 河北 三河 065201)
  • 收稿日期:2016-06-16 修回日期:2016-08-23 出版日期:2016-09-20 发布日期:2016-09-20
  • 作者简介:韩建坤(1971—),男,河北乐亭人,1995年毕业于长沙铁道学院,铁道工程专业,本科,高级工程师,主要从事隧道与地下工程施工技术与管理工作。Email: 3105268176@qq.com。

Study of Selection of Hydrological Conditions of Floating Transportation  and Sinking of Honggu Immersed Tunnel in Nanchang

HAN Jiankun   

  1. (Erchu Co., Ltd. of China Railway Tunnel Group, Sanhe 065201, Hebei, China)
  • Received:2016-06-16 Revised:2016-08-23 Online:2016-09-20 Published:2016-09-20

摘要:

沉管隧道工程管节浮运沉放对浮运水位和流速的要求高。南昌红谷隧道为国内首座内河中游沉管隧道,受季节降水影响,水位和流速变化幅度大,满足浮运条件的水文窗口较少。通过对管节受到的水流力和拖轮拖力计算,确定水文边界条件。采用声学多普勒流速剖面仪(ADCP)对浮运航道内关键点和控制断面流速、水位进行监测作为水文预报的基础。采用相应水位(流量)法和合成流量法相结合的方法预测隧址位置水位、流量,将预测的水位、流量结果导入数值计算模型计算浮运航道内的流场分布。现场实测表明,水位和流速预测误差为±30 cm、±0.15 m/s,满足管节浮运水文预报精度的要求,并有效指导浮运沉放水文窗口的选择,保障红谷隧道管节浮运沉放施工的安全。

关键词: 内河沉管隧道, 管节浮运沉放, 水文窗口, 水文预报

Abstract:

The requirements of water level and flow velocity of segment floating transportation and sinking of immersed tunnel are high. Due to seasonal rain, the water level and flow velocity in Ganjiang River vary greatly and there are few hydrological conditions suited to tunnel segment floating transportation and sinking. The boundary conditions of hydrology are obtained by calculating water resistance and towing force. The water level and flow velocity of key points and control crosssections are monitored by using acoustic Doppler Current Profilers (ADCP), and they are taken as the basis of hydrological forecasting. The water level and flow velocity are predicted by relevant water level method and compound flow rate method; and flow field distribution is calculated by numerical model based on predicted results. The field measured results show that the error of predicted water level and flow velocity are ±30 cm and ±0.15 m/s respectively; the hydrological prediction technologies can meet the accuracy requirements, and can guarantee the safety of segment floating transportation and sinking of Honggu Tunnel.

Key words: inland river immersed tunnel, segment floating transportation and sinking, hydrological window, hydrological forecast