• CSCD核心中文核心科技核心
  • RCCSE(A+)公路运输高质量期刊T1
  • Ei CompendexScopusWJCI
  • EBSCOPж(AJ)JST
二维码

隧道建设(中英文)

• • 上一篇    下一篇

高水压强透水地层盾构地中对接盾壳取芯钻孔工艺试验研究

张亚洲1, 2,姚占虎3,张习颖2,杨南2,梁玉强2   

  1. (1. 北京交通大学土木建筑工程学院,北京 100044; 2. 中交隧道工程局有限公司, 江苏 南京 211106; 3. 中交一公局集团有限公司, 北京 100024)
  • 出版日期:2026-09-08 发布日期:2026-09-08
  • 作者简介:张亚洲(1991—),男,湖南岳阳人,2016年毕业于河海大学,岩土工程专业,硕士,高级工程师,主要从事盾隧道工程设计与施工技术研究工作。E-mail:yazhouzhang321@163.com。

Experimental Study on Core Drilling Process of Shield Shell Joint in Shield Tunneling in High-Pressure Water-Permeable Strata

ZHANG Yazhou¹,², YAO Zhanhu³, ZHANG Xiying², YANG Nan², LIANG Yuqiang²   

  1. (1. School of Civil Engineering, Beijing Jiaotong University, Beijing 100044, China; 2. CCCC Tunnel Engineering Co., Ltd., Nanjing 211106, Jiangsu, China; 3. CCFH First Highway Engineering Group Co., Ltd., Beijing 100024, China)
  • Online:2026-09-08 Published:2026-09-08

摘要: 针对高水压强透水地层条件下盾壳钻孔精度难控、效率偏低、芯棒易掉落等关键技术难题,依托江阴靖江长江隧道工程,基于全站仪三维空间定位方法,搭建局部足尺模型试验平台,模拟先行盾构、后行盾构钻孔工况,设计不同角度钻孔、不同孔道形式、防芯棒掉落三类对比试验,系统开展盾壳取芯钻孔工艺试验研究。在利用全站仪完成孔位中心点确定的基础上,采用“四点一线”定位法辅以激光水准仪校准进行孔口管安装初步定位,再利用数显水平尺进行角度校核;同时提出预留孔道工艺、多钻进防芯棒掉落措施,形成适配复杂工况的施工技术体系。试验结果表明:1)采用“四点一线”定位法辅以激光水准仪校准,并配合试验数显水平尺进行角度复核,可将孔口管与水平面夹角偏差控制在±0.2°以内,小于设计要求的±0.3°;2)12.5°小角度工况下,机加工形成的光滑预留孔道较无预留孔道使钻孔效率提升631.62%,用时缩短91.86%;3)碳刨割除内封板导致的预留孔道表面不平整,虽会造成精度与工效发生一定程度的衰减,但角度偏差仍满足工程要求,综合工效远高于钻通内封板的方案;4)采用钻孔取通前关闭钻孔冲洗+多钻进200 mm的措施,实现了芯棒回收率100%。该工艺成功应用于实际工程现场363个孔位盾壳钻孔施工,取芯平均效率由36 mm/h提升至68 mm/h。研究成果为江阴靖江长江隧道工程高水压强透水地层条件下盾构地中对接盾壳钻孔施工提供了可靠的技术与数据支撑。

关键词: 盾构隧道, 地中对接, 盾壳钻孔, 高水压强透水地层, 钻孔工艺

Abstract: In response to the key technical problems such as difficult control of drilling accuracy, low efficiency, and easycore rod dropping in high water pressure and water-permeable stratum conditions, based on the Jiangyin Jingjiang Yangtze River Tunnel project, using the three-dimensional spatial positioning method of total station, a local full-scale model test platform was built to simulate the drilling conditions of the leading shield and the following shield. Three types of comparative tests were designed, including different angles of drilling, different hole channel forms, and measures to preventcore rods from falling off. Systematic research on the shield core drilling process was carried out. On the basis of determining the center point of the hole position using the total station, the "four points and one line" positioning method was adopted, supplemented by laser level instrument calibration for the initial positioning of the hole opening pipe, and then the angle was checked using a digital level ruler. At the same time, measures such as reserved hole channel technology and multi-drilling to preventcore rods from falling off were proposed to form a construction technology system suitable for complex conditions. The test results show: 1) By using the "four points and one line" positioning method supplemented by the laser level instrument calibration and combined with the test digital level ruler for angle verification, the deviation of the angle between the hole opening pipe and the horizontal plane can be controlled within ±0.2°, which is less than the design requirement of ±0.3°; 2) Under the 12.5° small angle condition, the machined smooth reserved hole channel compared with no reserved hole channel can increase the drilling efficiency by 631.62% and shorten the drilling time by 91.86%; 3) The surface of the reserved hole channel caused by carbon cutting to remove the inner sealing plate results in a certain degree of attenuation of accuracy and efficiency, but the angle deviation still meets the engineering requirements, and the comprehensive efficiency is much higher than the scheme of drilling through the inner sealing plate; 4) By closing the drilling hole before core sampling and multi-drilling 200 mm, thecore rod recovery rate can reach 100%. This technology was successfully applied to the shield drilling of 363 hole positions in the actual engineering site, and the average drilling efficiency of core sampling was increased from 36 mm/h to 68 mm/h. The research results provided reliable technical and data support for the shield ground-to-ground connection shield drilling in high water pressure and water-permeable stratum conditions under the Jiangyin Jingjiang Yangtze River Tunnel project.

Key words: shield tunnel, underground docking, shield shell drilling, high water pressure and highly permeable stratum, drilling process