摘要:
根据现场监控量测结果和对围岩压力、初支应力、结构内力的测试数据,分析了堡镇隧道极高地应力段软岩大变形的规律,及时调整相应施工参数,确保了施工安全。
Abstract:
On basis of the insitu monitoring results and the measured data of ground pressure, primary reinforcement stress and structure internal force, the pattern of the huge deformation of the soft ground in the extremelyhigh groundstressed portion of Baozhen tunnel is analyzed and the corresponding construction parameters are timely adjusted, which guarantees the construction safety.
中图分类号:
U456.3
张群健. 监测技术在堡镇隧道极高地应力段施工的应用[J]. 隧道建设, 2008, 28(2): 213-216.
ZHANG Qunjian. Application of Monitoring Technology in Construction of Extremelyhigh Groundstressed Portion of Baozhen Tunnel[J]. Tunnel Construction, 2008, 28(2): 213-216.