隧道建设(中英文) ›› 2008, Vol. 28 ›› Issue (4): 465-468,488.DOI: B

• 施工技术 • 上一篇    下一篇

双层双跨平顶直墙暗挖地铁风道二次衬砌施工关键技术

杨威虎1,2, 杜江1,3, 刘焕强1,2   

  1. 1. 中铁电气化局西安工程公司2. 北京交通大学 3. 石家庄铁道学院
  • 收稿日期:2008-01-07 修回日期:2008-05-22 出版日期:2008-08-20 发布日期:2009-11-23
  • 作者简介:杨威虎(1982—)|男|陕西省咸阳市人|北京交通大学在职硕士研究生|助理工程师|主要从事地铁施工技术管理工作。

Key Technology for Construction of Secondary Lining of Mined Metro Ventilation
Gallery with Double Story, Double Span, Flat Roof and Upright Wall

YANG Weihu 1,2,DU Jiang 1,3, LIU Huanqiang 1,2   

  1. 1. Xi’an Railway Engineering Co., Ltd, Electrification Bureau Group, CREC2. Beijing
    Jiaotong University3. Shijiazhuang Railway Institute
  • Received:2008-01-07 Revised:2008-05-22 Online:2008-08-20 Published:2009-11-23

摘要:

 大断面双层双跨平顶直墙暗挖地铁风道施工时具有开挖跨度相对较大,临时支护体系繁多,二次结构受力转换复杂的特点,针对北京地铁4号线石榴庄路站1#风道双层段的工程实践,分析总结大断面双层双跨平顶直墙结构中洞法开挖、受力转换、分块模筑等施工的几个关键技术环节,经实践检验,方案是合理的,可行的。

Abstract:

The construction of mined Metro ventilation gallery with large crosssection, double storey, double span, flat roof and upright wall has such features as relatively large excavation span, complex temporary support system and complex loadshifting of the secondary lining structure. Taking the construction of the doublestorey section of No. 1 ventilation gallery of Shiliuzhuang Road Station on Line 4 of Beijing Metro as example, the authors summarize the key construction technology for the ventilation gallery with large crosssection, double storey, double span, flat roof and upright wall in terms of central drift excavation method, load shifting and sectionbysection construction of the insitu cast concrete lining. The project practice shows that the construction plan is reasonable and feasible.

Key words: doublestorey, doublespan, flat roof, upright wall, miningsecondary castinsitu concrete liningload shift, ventilation gallery of Metro workssupport replacementdemolition