台北捷运新庄线隧道受毗邻建物深开挖影响案例探讨

  

  1. 1.台北市政府捷运工程局;2.台北市政府捷运工程局北区工程处;
    3.开南大学空运管理学系暨研究所、运输与决策研究中心
  • 收稿日期:2007-06-06 出版日期:2007-08-10 发布日期:2010-04-20
  • 作者简介:朱旭|男|硕士|现任副局长|主要从事捷运系统兴建管理工作及潜盾隧道专题研究。 谢宇珩|男|硕士|现任总工程司|主要从事捷运系统兴建管理及地下工程防水研究。 古鸿坤|男|硕士|现任副工程司|主要从事捷运系统兴建管理工作及厂商管理研究。 孙国勋|男|博士|现任副教授兼运输与决策研究中心主任|主要从事工程项目管理方面的研究工作。

The Case Study of the Influence of the Deep Excavation
of Nearby Buildings on the Tunnel at Taipei MRT Xinzhuang Line

  1. 1.The Department of Rapid Transit Systems of the Taipei City Government;
    2.North District Project Office, the Department of Rapid Transit Systems, Taipei City Government;
    3.Department of Air Transportation, Kainan University
  • Received:2007-06-06 Online:2007-08-10 Published:2010-04-20

摘要:

台北捷运新庄线丹凤站至辅大站间隧道在完成钻掘工作后,因某建设公司错估隧道与基地建筑线之实际距离,又于施作中正路侧连续壁时发生坍孔,以致在其抢救过程中,造成位于中正路下方之捷运隧道,因灌浆压力挤压使得隧道上方部分环片向内变形。经现场详细检视受损隧道情形,发现于该建物新建工程之基地投影范围内之环数第439至第471环中,除第462环至第470环因变形量超出钢筋之安全负荷需进行环片补强外,另第459环因环片产生之裂缝在行车方向亦需补强。经结构计算后,本案受损环片自第459环至第470环皆采内衬钢环片进行补强,详载整个事件自开始至处理完成之过程,以作为日后类似工程处理之参考。

关键词: 隧道变形 深开挖 毗邻建物

Abstract:

After the excavation of the tunnel between the FuJen University station and the Danfeng station of Taipei MRT Xinzhuang line, the construction company underestimated the real distance from the tunnel to the structure line of the base and a series mistakes happened on ChungCheng road when constructed. As a result of these factors, the upper segment loop of at the MRT tunnel beneath the ChungCheng road has been out of shape inwards due to the overpressure of grouting during the process of the urgent steps of salvage. Being careful examination of the damage of the tunnel at the site, the 439th to 471st loops have been unearthed under the projection of the newly constructed project. Besides the 462nd loop to the 470th are overdeformed exceeding the safety range of the steel bar and need to be repaired. In addition, the 459th loop needs to be repaired for the fissure in the direction of movement of vehicles. Under the calculation of the structural mechanics, the damaged loops for the 459th to the 470th are need to be repaired by the means of lining the copper loops. This article reports the process of repairing the deformed tunnels form beginning to end to be a reference of the relevant work projects afterwards.

Key words: shield tunnel  rapid transit systems  deformed tunnel deep excavation  nearby buildling