Construction Technologies for Connection Galleries of Shieldbored Tunnels under Bad Geological Conditions
Received date: 2012-07-28
Revised date: 2012-10-15
Online published: 2013-02-19
张君 . 不良地质条件下盾构区间隧道联络通道施工技术[J]. 隧道建设, 2012 , 32(增刊1) : 95 -98 . DOI: 10.3973/j.issn. 1672-741X.2012.z1.020
The construction difficulties of connection galleries and waste water pump room are presented, with the construction of connection galleries of shieldbored tunnel on Yitian stationShixia station section of 3151 bid section of Shenzhen Metro as an example. Jet grouting reinforcement technology is replaced by fullface grouting reinforcement technology. The construction technology and technical key points of fullface grouting reinforcement technology are presented. The successful construction of connection galleries of shieldbored tunnel under bad geological conditions is guaranteed after construction program optimization.
Key words: tunnel; connection gallery; shieldbored tunnel section; grouting; support; secondary lining
/
| 〈 |
|
〉 |