Grouting Consolidation Technologies for Disassembling Jammed TBM Cutter Head in Waterrich and Silty Sand Stratum
Received date: 2012-08-16
Revised date: 2012-11-20
Online published: 2013-02-19
葛寨辉 . 富水粉细砂层拆除被困TBM刀盘注浆加固技术[J]. 隧道建设, 2012 , 32(增刊2) : 105 -110 . DOI: 10.3973/j.issn.1672-741X.2012.z2.021
The TBM often jammed due to the overlarge thrusting force and torque induced by collapse of working face and overlarge mucking during TBM boring in waterrich and silty sand stratum. The ground ahead of cutter head is grouting consolidated, so as to successfully disassembling the jammed TBM. The watercontaining rate of the ground is reduced, the stability of the ground is improved and the successful and safe disassembling of cutter head is guaranteed.
Key words: water rich; silty sand; sand bursting; TBM jamming; cutter head; grouting consolidation
/
| 〈 |
|
〉 |