敞开式TBM在重庆轨道交通6号线的应用分析
收稿日期: 2012-11-10
修回日期: 2012-12-05
网络出版日期: 2013-03-05
Analysis on Application of Open TBM in No. 6 Line of Chongqing MRT Project
Received date: 2012-11-10
Revised date: 2012-12-05
Online published: 2013-03-05
张红耀 , 刘东亮 . 敞开式TBM在重庆轨道交通6号线的应用分析[J]. 隧道建设, 2013 , 33(2) : 160 -164 . DOI: 10.3973/j.issn.1672-741X.2013.02.013
The applicability of TBM in line 6 of Chongqing MRT project is a key point for the successful construction of the project. In the TBM design phase, the cutter head and cutting tools, the main bearing, the support system and the belt conveyor system of the TBM are specially designed to cope with the specific rock geological conditions. The main problems occurring in the TBM boring phase, such as problems in shotcreting, belt conveyor mucking system, vertical material transportation system, cutter head and cutting tools and interference between tunnel lining and Metro station construction, are discussed and countermeasures are proposed. The practice shows that the applicability of the open TBM in rock geology is improved due to the special design of the equipment and the countermeasures taken.
Key words: open TBM; MRT in Chongqing; rock geology; design
/
| 〈 |
|
〉 |