南水北调中线穿黄工程二次衬砌预应力环形张拉施工技术
收稿日期: 2012-11-23
修回日期: 2013-03-15
网络出版日期: 2013-04-12
Technology for Circular Prestress Tensioning of Secondary Lining of Tunnels: Case Study on Yellow Rivercrossing Tunnel on Central Route of Southtonorth Water Transfer Project
Received date: 2012-11-23
Revised date: 2013-03-15
Online published: 2013-04-12
蒋元勇 . 南水北调中线穿黄工程二次衬砌预应力环形张拉施工技术[J]. 隧道建设, 2013 , 33(4) : 305 -308 . DOI: 10.3973/j.issn.1672-741X.2013.04.009
The Yellow rivercrossing tunnel on the central route of southtonorth water transfer project is a pressured water transfer tunnel. The tunnel is excavated by shield machines, with the segment lining as the primary reinforcement. Prestressed castinsitu concrete lining is installed for the tunnel as the final lining so as to ensure the safety of the tunnel structure. Prestressing ducts are embedded in the castinsitu lining concrete, steel stands are installed and circular tensioning is made to achieve the prestressing of the lining concrete. In this paper, the process, technical requirements, key points and countermeasures for the tensioning are presented. The relationship between the extended length of the steel strands and the friction coefficient is obtained by means of model calculation and data setting. The practice shows that the circular tensioning technology used in Yellow rivercrossing tunnel can meet the requirements of safety of the water transfer structure.
/
| 〈 |
|
〉 |