中天山隧道TBM长距离施工通风方案研究
收稿日期: 2013-03-11
修回日期: 2013-04-19
网络出版日期: 2013-05-16
Case Study on Longdistance Ventilation of Zhongtianshan Tunnel Driven by TBM
Received date: 2013-03-11
Revised date: 2013-04-19
Online published: 2013-05-16
朵生君 . 中天山隧道TBM长距离施工通风方案研究[J]. 隧道建设, 2013 , 33(5) : 419 -422 . DOI: 10.3973/j.issn.1672-741X.2013.05.015
Zhongtianshan tunnel is 22.449 km long. The 13.8 km entrance section of the tunnel is driven by TBM. Longdistance ventilation during tunneling is one of the important factors that affect the construction progress and economic efficiency. Study is made on the ventilation of Zhongtianshan tunnel on basis of the construction method, driving length and construction organization of the tunnel. Comparison and contrast is made between singledirection longdistance ventilation program and gallerytype combined ventilation program, which indicates that the gallerytype combined ventilation program is the optimum ventilation program. The stage division and number of the ventilation fans needed for the gallerytype combined ventilation program are proposed. The ventilation program is further adjusted during tunneling in accordance with the site ventilation monitoring results so as to meet the actual conditions of the site. In the end, the ventilation program adopted guarantees the successful breakthrough of Zhongtianshan tunnel.
/
| 〈 |
|
〉 |