高地应力条件下深埋隧道开挖方式数值优选及工程应用
收稿日期: 2013-04-26
修回日期: 2013-06-09
网络出版日期: 2013-09-18
Numerical Optimization on the Selection of Excavation Methods for Deep Tunnels in High Stress Field and its Engineering Application
Received date: 2013-04-26
Revised date: 2013-06-09
Online published: 2013-09-18
杨彦亮 , 李锡波 , 毛洪录 . 高地应力条件下深埋隧道开挖方式数值优选及工程应用[J]. 隧道建设, 2013 , 33(9) : 735 -740 . DOI: 10.3973/j.issn.1672-741X.2013.09.006
To avoid rock falls and distortion of support structure occurring in the construction of tunnels in high stress field, the designers had plans to use either stage excavation or pilot heading excavation method for the tunnel. Full face excavation method, pilot heading excavation method and stage excavation method were simulated by the finite difference software FLAC3D. After analyzing and comparing the features of the distribution of the deformation field, plasticized deformation field and stress field, the stage excavation method was proposed for the tunnel based on the data produced. After adopting the said method, the stability of the excavation face was improved dramatically and the data collected at the site coincide well with the numerical simulation results.
/
| 〈 |
|
〉 |