广州地铁广佛线盾构隧道穿越桥梁桩基施工技术
收稿日期: 2013-06-29
修回日期: 2013-07-25
网络出版日期: 2013-09-18
A Case Study on How to Deal with Existing Bridge Piles in Shield Tunneling
Received date: 2013-06-29
Revised date: 2013-07-25
Online published: 2013-09-18
李幸发 . 广州地铁广佛线盾构隧道穿越桥梁桩基施工技术[J]. 隧道建设, 2013 , 33(9) : 791 -800 . DOI: 10.3973/j.issn.1672-741X.2013.09.015
The shield machine came across existing bridge piles while boring from Shayong station to Shayuan station of the Guangzhou~Foshan line of Guangzhou Metro. It was of great importance to ensure the structural safety of the tunnel and the safety and normal function of the bridge. The following countermeasures were adopted to deal with the existing bridge piles: 1) The tunnel section was excavated by the mining method; 2) The reserved bedrock underneath the existing bridge piles was reinforced from inside the mined tunnel; the existing bridge piles were then properly connected to the secondary lining of the mined tunnel before the piles inside the tunnel were cut off; 3) The shield machine went through the mined tunnel and the segments were erected. The analysis on the monitoring data demonstrated that the countermeasures used here were feasible and rational. This paper provides reference for similar projects in the future.
/
| 〈 |
|
〉 |