Optimization of Construction Program of Shield Launching Shaft to Achieve Earlier Shield Launching: Case Study on Shield Launching Shaft of Anhuaqiao Station Andelibeijie Station Section of Line 8 of Beijing Metro
Received date: 2013-08-12
Revised date: 2013-11-08
Online published: 2013-12-27
袁创辉 , 姜娜 , 李立 . 北京地铁8号线安—安区间明挖盾构始发井快速提供始发条件技术探讨[J]. 隧道建设, 2013 , 33(12) : 1029 -1035 . DOI: 10.3973/j.issn.1672-741X.2013.12.009
With the development of urban rail transit works, more and more shield tunnels are built. Due to the tight construction schedule of the shield tunnels, how earlier shield launching can be achieved in the shield launching becomes the focus of the designer and the contractor. The originallydesigned concrete structure of the first and second underground floors of the shield launching shaft of Anhuaqiao StationAndelibeijie Station Section of Line 8 of Beijing Metro is cancelled and reinforced concrete waling is used to replace the originallydesigned steel bracing, and earlier shield launching is achieved. During the construction of the project, the ground surface settlement is monitored. The monitoring results show that the maximum settlement of the ground surface surrounding the shield launching shaft is 6.42 mm, and the settlement of the utility lines is less than 1 mm. The practice shows that reinforced concrete waling can be used to replace the originallydesigned steel bracing, so as to achieve earlier shield launching.
/
| 〈 |
|
〉 |