引水洞爆破施工对既有隧道衬砌的影响分析
收稿日期: 2013-12-08
修回日期: 2014-02-28
网络出版日期: 2014-03-20
Analysis on Influence on Lining of Existing Railway Tunnel Imposed by Blasting Construction of Waterreleasing Tunnel
Received date: 2013-12-08
Revised date: 2014-02-28
Online published: 2014-03-20
孔景华 . 引水洞爆破施工对既有隧道衬砌的影响分析[J]. 隧道建设, 2014 , 34(3) : 221 -225 . DOI: 10.3973/j.issn.1672-741X.2014.03.007
Due to the high water pressure in the karst cave area, water seepage occurs to a railway tunnel after it has been put into operation. Two waterreleasing tunnels are excavated on top of the mentioned railway tunnel to intercept the karst water and to reduce the load on the tunnel lining, so as to solve the water seepage problem. In the paper, the blasting construction of the waterreleasing tunnel is presented, the loading on and deformation of the main railway tunnel during the construction of the waterreleasing tunnel are analyzed on basis of the results of the monitoring of the blasting vibration, the structural deformation, the surrounding rock pressure, the stress on the shapedsteel arches and the strain of the concrete lining. The analysis shows that both the blasting vibration velocity and the stress on the main railway tunnel structure are within the allowed standard, the deformation of the main railway tunnel structure is small and the loading on the main railway tunnel structure is relatively stable. It is concluded that the influence of the blasting construction of the waterreleasing tunnel on the main railway tunnel is small and the normal operation of the railway line can be guaranteed.
/
| 〈 |
|
〉 |