修建城际地下铁路隧道存在的步距问题与相关建议

  • 聂振宇
展开
  • (中交集团第一公路工程局厦门工程有限公司, 广东东莞 523400) 
聂振宇(1983—),男,江西九江人,2006年毕业于西南交通大学,土木工程专业,本科,工程师,现从事城市地铁施工工作。

收稿日期: 2013-12-03

  修回日期: 2014-02-24

  网络出版日期: 2014-04-25

Comments on Distance between Primary Support/Secondary Lining and Working Face of Intercity Underground Railway Tunnels

  • NIE Zhenyu
Expand
  • (Xiamen Engineering Co., Ltd. of CCCC First Highway Engineering Bureau, Dongguan 523400, Guangdong, China)

Received date: 2013-12-03

  Revised date: 2014-02-24

  Online published: 2014-04-25

摘要

以莞惠城际轨道交通工程松山湖隧道施工为例,通过对隧道各工序作业时间分析、隧道设计与施工类比和施工模型图说明,认为铁建设[2010]120号文在修建城际地下铁路隧道方面尚存在一定的适应性和可操作性的问题,并提出以下建议: 1)Ⅵ级围岩隧道,初期支护封闭成环位置距离掌子面由原35 m调整为50 m,二次衬砌距离掌子面由原70 m调整为85 m(除文中所述几种特殊情况外); 2)Ⅴ级围岩隧道,初期支护封闭成环位置距离掌子面由原35 m调整为55 m,二次衬砌距离掌子面由原70 m调整为90 m; 3)Ⅳ级围岩隧道,初期支护封闭成环位置距离掌子面由原35 m调整为65 m,二次衬砌距离掌子面由原90 m调整为120 m。

本文引用格式

聂振宇 . 修建城际地下铁路隧道存在的步距问题与相关建议[J]. 隧道建设, 2014 , 34(4) : 356 -361 . DOI: 10.3973/j.issn.1672-741X.2014.04.011

Abstract

In this article, the construction cycle time and construction model of Songshanhu tunnel on DongguanHuizhou intercity railway are analyzed, and comparison and contrast is made between national railway tunnels and intercity railway tunnel. It is believed that the requirements specified in Tiejianshe No. [2010]120 are not applicable to the construction of intercity railway tunnels. Proposals made are follows: 1) For intercity railway tunnels in Grade Ⅵ surrounding rock, the distance between the primary support and the working face should be optimized from 35 m to 50 m, and the distance between the secondary lining and the working face should be optimized form 70 m to 85 m; 2) For tunnels in Grade Ⅴ surrounding rock, the distance between the primary support and the working face should be optimized from 35 m to 55 m, and the distance between the secondary lining and the working face should be optimized form 70 m to 90 m; 3) For tunnel in Grade Ⅳ surrounding rock, the distance between the primary support and the working face should be optimized from 35 m to 65 m, and the distance between the secondary lining and the working face should be optimized from 90 m to 120 m. 