深圳地铁11号线车公庙枢纽高强度岩层中型钢立柱施工关键技术
收稿日期: 2013-11-27
修回日期: 2014-03-11
网络出版日期: 2014-04-25
Case Study on Installation of Shaped Steel Columns in Highstrength Rocks in Construction of Chegongmiao Station of Line 11 of Shenzhen Metro
Received date: 2013-11-27
Revised date: 2014-03-11
Online published: 2014-04-25
陈瑜 , 李海龙 . 深圳地铁11号线车公庙枢纽高强度岩层中型钢立柱施工关键技术[J]. 隧道建设, 2014 , 34(4) : 362 -367 . DOI: 10.3973/j.issn.1672-741X.2014.04.012
In the construction of Chegongmiao Station of 11301 bid section of Line 11 of Shenzhen Metro, shaped steel columns need to be installed rapidly and accurately into highstrength rocks (with 120 MPa uniaxial compressive strength) The following two key technologies are adopted to fulfill the difficult job: 1) Advanced coretaking drilling rig is used and special core taking process is adopted so that large diameter (with 20 m diameter) boreholes can be drilled rapidly in the highstrength rocks (with 15~20 m cyclic drilling rate); 2) The method of installing the crossshaped steel columns after concrete casting is used so that the shaped steel columns can be installed rapidly and accurately In the end, the job has been fulfilled successfully
/
| 〈 |
|
〉 |