大连地铁2号线小半径曲线隧道盾构单井口始发技术研究
收稿日期: 2013-01-20
修回日期: 2014-06-13
网络出版日期: 2014-09-22
Shield Launching Technology for Running Tunnel on Smallradius Curve with One Single Shaft: Case Study on Line 2 of Dalian Metro
Received date: 2013-01-20
Revised date: 2014-06-13
Online published: 2014-09-22
季维果 . 大连地铁2号线小半径曲线隧道盾构单井口始发技术研究[J]. 隧道建设, 2014 , 34(9) : 895 -899 . DOI: 10.3973/j.issn.1672-741X.2014.09.012
The running tunnel from Xi’an Road Station to Jiaotong University Station on Line 2 of Dalian Metro is on smallradius curves. The shield for the mentioned running tunnel is to be launched under the condition of one single shaft. In the paper, comparison and contrast is made between separate shield launching program and integral shield launching program in terms of progress, cost and feasibility, and it is finally determined that integral shield launching program is to be adopted. In the launching of the shield, selfmade belt conveyor and selfmade segment feeder are used, and the launching direction and the driving attitude of the shield are well controlled, so as to facilitate the mucking, segment delivery and shield attitude control in the launching. In the end, successful shield launching is achieved for the running tunnel on smallradius curves.
/
| 〈 |
|
〉 |