Countermeasures for Floating of Largediameter Slurry Shield Tunnel in Soft Soil
Received date: 2013-12-23
Revised date: 2014-10-09
Online published: 2014-12-17
王新 , 李庭平 , 王印昌 . 软土大直径泥水盾构隧道施工期上浮的控制措施[J]. 隧道建设, 2014 , 34(12) : 1168 -1174 . DOI: 10.3973/j.issn.1672-741X.2014.12.009
Due to the shallow overburden near the working shaft, tunnel floating often occurs when a largediameter slurry shield bores adjacent to the working shaft. In this paper, the physical environment and operation techniques of slurry shield that affect the floating of shieldbored tunnels are analyzed, with considering the design experience of slurry shieldbored tunnels in soft soil area. The study results show that the main factors that affect the tunnel floating include ground water, simultaneous grouting, shield attitude control, ground reaction and grout backflowing; the main factors that have indirect influence on the tunnel floating include overburden thickness, ground water level, tunnel dimension, material density, overburden compression characteristics, shield boring speed and segment joint stiffness; main countermeasures for tunnel floating include installing artificial overburden, optimizing the shield boring parameters and shield attitude control, installing floatingresistant portal structures, improving the grouting techniques and the grout performance, carrying out secondary grouting and strengthening the longitudinal connections between segments.
/
| 〈 |
|
〉 |