盾构隧址区无自由面基岩孤石爆破预处理技术炸药单耗确定研究
收稿日期: 2014-12-17
修回日期: 2015-01-29
网络出版日期: 2015-03-20
Study on Determination of Unit Consumption of Explosives in Pretreatment of Bedrock/boulders along Alignment of Shieldbored Tunnel without Free Surface
Received date: 2014-12-17
Revised date: 2015-01-29
Online published: 2015-03-20
刘洪震 . 盾构隧址区无自由面基岩孤石爆破预处理技术炸药单耗确定研究[J]. 隧道建设, 2015 , 35(3) : 215 -219 . DOI: 10.3973/j.issn.1672-741X.2015.03.004
The bedrock/boulders along the alignment of shield tunneling cannot be excavated directly by the cutterhead of the shield, therefore they have to be treated in advance. In the construction of the diversion tunnel of Taishan Nuclear Plant in Guangdong, China, the bedrock/boulders along the tunnel alignment have to be blasted in advance. In the paper, the unit consumption of the explosives for the blasting is studied by means of theoretical deduction and field test and a calculation formula is obtained. The formula has been used in the engineering practice and good result has been achieved.
Key words: shield; without free surface; bedrock; boulder; blasting
/
| 〈 |
|
〉 |