大跨平顶直墙暗挖通道二次衬砌技术探析
收稿日期: 2014-11-21
修回日期: 2015-01-20
网络出版日期: 2015-03-20
Technology for Secondary Lining of Largespan Flatroof Straightwall Tunnels
Received date: 2014-11-21
Revised date: 2015-01-20
Online published: 2015-03-20
田海波 . 大跨平顶直墙暗挖通道二次衬砌技术探析[J]. 隧道建设, 2015 , 35(3) : 268 -273 . DOI: 10.3973/j.issn.1672-741X.2015.03.013
The excavation and secondary lining of flatroof straightwall tunnels with shallow overburden have great risks. In the paper, the applicability of the flatroof straightwall tunnels is analyzed. Three methods for the installation of the secondary lining of flatroof straightwall tunnels are compared in terms of span, excavation method, risk and construction period, with a mined flatroof straightwall underpass of a Metro works as an example. The advantages, disadvantages and application conditions of the mentioned three methods are summarized. The installation method and steps for the secondary lining of mined flatroof straightwall structures under the condition that the support is not removed are proposed. The key points of the design of mined flatroof straightwall tunnels are summarized and the principle for the node treatment is proposed.
/
| 〈 |
|
〉 |