引松供水工程超大直径竖井超深孔反向爆破成井施工技术
收稿日期: 2015-06-09
修回日期: 2015-07-24
网络出版日期: 2015-09-22
Case Study on Raise Boring of a Superlarge Diameter Vertical Shaft of Songhuajiang River Water Conveyance Project
Received date: 2015-06-09
Revised date: 2015-07-24
Online published: 2015-09-22
孙振川 , 王亮 . 引松供水工程超大直径竖井超深孔反向爆破成井施工技术[J]. 隧道建设, 2015 , 35(9) : 897 -906 . DOI: 10.3973/j.issn.1672-741X.2015.09.007
Yinmahe surge shaft in No. 4 bid section of Songhuajiang River Water Conveyance Project is a cylindrical vertical shaft with 50 m depth and 20 m diameter. The shaft is located in tuffaceous sandstone. Due to the steep landforms and complex conditions at the ground surface around the shaft, it is very difficult to establish the access roads and construction sites for the shaft, and it is very difficult to mobilize the heavyduty equipment to the site. After extensive literature survey and study, raise boring method is adopted for the shaft. In the paper, the technologies for the raise boring technologies, including the blasting zone division, blasting scheme and key blasting techniques, are presented. In the end, the shaft has been completed successfully.
Key words: water supply project; surge shaft; superlarge diameter; super depth; raise boring
/
| 〈 |
|
〉 |