沈家门港海底沉管隧道浮运、沉放施工控制技术
收稿日期: 2015-06-08
修回日期: 2015-08-14
网络出版日期: 2015-09-22
Control Technology for Towing and Sinking of Immersed Tubes: Case Study on Shenjiamen Port Subsea Tunnel
Received date: 2015-06-08
Revised date: 2015-08-14
Online published: 2015-09-22
邓建林 . 沈家门港海底沉管隧道浮运、沉放施工控制技术[J]. 隧道建设, 2015 , 35(9) : 914 -919 . DOI: 10.3973/j.issn.1672-741X.2015.09.009
Shenjiamen port subsea tunnel is the first subsea passenger tunnel in mainland China built by immersed tube method. In the paper, the influence of the waves and tides on the construction of the subsea tunnel is presented, proper tube towing method and proper tube sinking method are selected on basis of mechanical calculations and analysis, proper construction window time is determined, and the key points in the towing, sinking, connection and backfilling of the tubes are analyzed. In the end, the tunnel has been completed successfully.
Key words: immersed tube tunnel; towing; sinking; construction control technology
/
| 〈 |
|
〉 |