长沙—株洲—湘潭城际铁路湘江隧道开滨盾构区间富水基岩地层管片背后注浆技术研究
收稿日期: 2015-05-22
修回日期: 2015-08-05
网络出版日期: 2015-09-22
Backfilling Grouting Technology for Shieldbored Tunnel in Waterrich Bedrock Strata: Case Study on Xiangjiang Tunnel on ChangshaZhuzhouXiangtan Intercity Railway
Received date: 2015-05-22
Revised date: 2015-08-05
Online published: 2015-09-22
任成国 . 长沙—株洲—湘潭城际铁路湘江隧道开滨盾构区间富水基岩地层管片背后注浆技术研究[J]. 隧道建设, 2015 , 35(9) : 935 -938 . DOI: 10.3973/j.issn.1672-741X.2015.09.012
Backfilling grouting behind the segments is the key technology to ensure the safety and construction quality of the shieldbored tunnel, is the key technology to control the ground settlement, and is closely related to the construction cost. Xiangjiang tunnel on ChangshaZhuzhouXiangtan intercity railway is a large diameter shield bored tunnel crossing waterrich bedrock strata. Due to the big annular space behind the segment rings and the flushing erosion effect of the ground water, the simultaneous grouting carried out cannot achieve the expected result. In the paper, the causes for the problems in the simultaneous grouting are analyzed, and countermeasures including “simultaneous grouting, complementary grouting, secondary consolidation grouting and sealing ring execution” are taken and optimized during the tunneling. In the end, the safety and grouting quality are ensured and the construction cost is effectively reduced.
/
| 〈 |
|
〉 |