南昌红谷沉管隧道干坞坞底施工技术
收稿日期: 2015-05-26
修回日期: 2015-07-15
网络出版日期: 2015-09-22
Construction Technology for Bottom of Dry Dock of Honggu Immersed Tunnel in Nanchang
Received date: 2015-05-26
Revised date: 2015-07-15
Online published: 2015-09-22
赵康林 , 王秋林 , 崔玉国 . 南昌红谷沉管隧道干坞坞底施工技术[J]. 隧道建设, 2015 , 35(9) : 949 -956 . DOI: 10.3973/j.issn.1672-741X.2015.09.015
The difficulties in the construction of the bottom of the dry dock of Honggu tunnel in Nanchang are presented. Countermeasures, including proper zone division of the dry dock bottom, zonal replacement filling, adopting angle steel for the sleeper beam, floating layers consisting of concrete and filtering channels and proper optimization of the drainage system, are adopted. In the end, the construction of the bottom of the dry dock has been completed successfully and relevant requirements have been complied with.
/
| 〈 |
|
〉 |