舟山灌门海底隧道方案研究
收稿日期: 2015-08-13
修回日期: 2015-08-27
网络出版日期: 2015-12-24
Study on Options of Guanmen Subsea Tunnel in Zhoushan
Received date: 2015-08-13
Revised date: 2015-08-27
Online published: 2015-12-24
刘佳 , 吴德兴 , 高翔 . 舟山灌门海底隧道方案研究[J]. 隧道建设, 2015 , 35(S2) : 57 -62 . DOI: 10.3973/j.issn.1672-741X.2015.S2.011
Guanmen subsea tunnel in Zhoushan is the key work of the project connectiing Daishan County and Zhoushan Island. The tunnel crosses Guanmen watercourse. The geological investigation reveals that the average depth of the water at the tunnel site is 35 m, with the maximum depth reaching 53.8 m. The sea bed at the tunnel site fluctuates dramatically and the water depth varies greatly. Furthermore, there are 3 largescale fracture zones at the tunnel site, where the rock conditions have great impact on the tunnel. In the paper, comparison and contrast is made between two subsea tunnel options, i.e., subsea tunnel constructed by drill and blast method and that constructed by shield machine. In the end, the option of subsea tunnel constructed by shield machine is proposed.
Key words: subsea tunnel; fracture zone; drill and blast method; shield machine
/
| 〈 |
|
〉 |