长春地铁解放大路站基于三维数值模拟的地铁车站施工工法优化分析
收稿日期: 2015-07-02
修回日期: 2015-09-25
网络出版日期: 2016-02-01
基金资助
吉林大学横向课题(3R1133142417)
Optimization of Construction Methods for Jiefanglu Station of Changchun Metro Using Threedimensional (3D) Numerical Simulations
Received date: 2015-07-02
Revised date: 2015-09-25
Online published: 2016-02-01
戴文亭 , 武皓 , 孙明志 , 郝佰洲 , 曹耀兮 . 长春地铁解放大路站基于三维数值模拟的地铁车站施工工法优化分析[J]. 隧道建设, 2016 , 36(1) : 12 -19 . DOI: 10.3973/j.issn.1672-741X.2016.01.002
In this paper, comparison and contrast is made among three constructions methods, i.e., 6pilot PBA method, 8pilot PBA method, and cast insitu arch and cutandcover topdown method, in terms of ground surface settlement above tunnel axial line, crown settlement and crown stress. The numerical simulation model of Jiefanglu Station of Changchun Metro is established, so as to analyze the optimization of construction method. The study results show that: 1) The ground surface settlement above the tunnel axial line, crown settlement and crown stress of the three construction methods are different; 2) The cast insitu arch and cutandcover topdown method is superior to 6pilot PBA method and 8pilot PBA method for this project, and the 6pilot PBA method is the worst. The results achieved can provide reference for construction of similar projects in the future.
/
| 〈 |
|
〉 |