接收车站封闭条件下盾构拆机解体技术探析
收稿日期: 2015-08-24
修回日期: 2015-10-20
网络出版日期: 2016-05-25
Analysis of Shield Dismantling Method under Conditions of Closed Receiving Shaft
Received date: 2015-08-24
Revised date: 2015-10-20
Online published: 2016-05-25
李海 , 朱长松 . 接收车站封闭条件下盾构拆机解体技术探析[J]. 隧道建设, 2016 , 36(5) : 619 -626 . DOI: 10.3973/j.issn.1672-741X.2016.05.019
The shield should be transported to launching shaft in tunnel after dismantling when the receiving shaft has been closed. As a result, a series of shield dismantling methods for 6 390 mm EPB shield used in Line No. 6 of Tianjin Metro, including cutterhead dismantling, front shield dismantling, shield body dismantling and shield tail dismantling, are designed and applied; and the shield transport in tunnel can be achieved. The abovementioned shield dismantling methods can provide reference and guidance for similar projects in the future.
/
| 〈 |
|
〉 |