土压平衡盾构接收脱困施工技术研究
收稿日期: 2015-12-28
修回日期: 2016-06-14
网络出版日期: 2016-07-27
Jam Releasing Technologies for Earth Pressure Balance Shield in Shield Receiving Shaft
Received date: 2015-12-28
Revised date: 2016-06-14
Online published: 2016-07-27
李海 , 朱长松 , 赵大朋 . 土压平衡盾构接收脱困施工技术研究[J]. 隧道建设, 2016 , 36(7) : 872 -876 . DOI: 10.3973/j.issn.1672-741X.2016.07.017
The jam releasing technologies for earth pressure balance (EPB) shield in shield receiving shaft applied to Tianjin Metro Line No.3 are introduced. The jam releasing technologies include drag reduction hole drilling after chamber opening under atmospheric pressure, thrusting force increaing by setting external pump station and cylinder and using separating jam releasing method. The advantages and disadvantages of abovementioned technologies and their applicable fields are analyzed. Good effects have been achieved. The results can provide reference for jam releasing of shield of similar projects in the future.
/
| 〈 |
|
〉 |