TBM拆卸洞及拆机起重系统优化设计研究
收稿日期: 2016-06-29
修回日期: 2016-09-12
网络出版日期: 2017-03-04
Research on Optimization of Design of TBM Disassembling Cavern and Hoisting System
Received date: 2016-06-29
Revised date: 2016-09-12
Online published: 2017-03-04
黄金光 . TBM拆卸洞及拆机起重系统优化设计研究[J]. 隧道建设, 2017 , 37(2) : 242 -249 . DOI: 10.3973/j.issn.1672-741X.2017.02.018
The TBM disassembling cavern is usually located in tunnel with large crosssection; and it has overhead traveling crane. The construction of large crosssection TBM disassembling cavern is difficult; the construction schedule is long and the construction cost is high. In order to shorten the construction schedule of TBM disassembling cavern and reduce the TBM disassembling time, a more adaptable hoisting system of electric hoist + inverted chain is developed in the TBM disassembling of Zhongtianshan Tunnel on the second line of TurpanKorla section of Nanjiang Railway. The anchor bolt is set on tunnel crown top so as to fasten the guide rail and independent hoisting points. The optimized type and size of crosssection structure of TBM disassembling cavern are decided by comparison between original design scheme and optimized scheme. The area of optimized crosssection of TBM disassembling cavern is reduced by 1/3; and the rapid TBM disassembling is reached.
/
| 〈 |
|
〉 |