软土地层土压平衡式盾构盾尾有限元分析及优化对策
收稿日期: 2017-01-17
修回日期: 2017-03-31
网络出版日期: 2017-05-27
Finite Element Analysis and Optimization Countermeasures for Shield Tail of Earth Pressure Balanced Shield in Soft Stratum
Received date: 2017-01-17
Revised date: 2017-03-31
Online published: 2017-05-27
邵成猛 . 软土地层土压平衡式盾构盾尾有限元分析及优化对策[J]. 隧道建设, 2017 , 37(S1) : 26 -31 . DOI: 10.3973/j.issn.1672-741X.2017.S1.005
The shield tail bears large water pressure and dead load during shield tunneling, which would induce shield tail deformation. Incidents would be occurred when the shield tail deformation is beyond design requirement. The loads on shield tail during shield tunneling are analyzed, and 3D finite element model is established and calculated. The shield tail structure is optimized by replacing 4 grouting holes by 6 grouting holes, and finite element software is used to analyze the construction cases respectively. The analytical results show that the shield tail deformation is reduced and the shield tunneling quality is improved by adopting 6 grouting holes.
/
| 〈 |
|
〉 |