复杂地形条件下桥隧相连隧道洞口结构设计研究

  • 万俊峰 ,
  • 李冬生
展开
  • (1. 蒙西华中铁路股份有限公司, 北京 100073; 2. 中国铁路设计集团有限公司, 天津 300142)
万俊峰(1968—),男,河南漯河人,1990年毕业于石家庄铁道学院,隧道与地下工程专业,本科,高级工程师,主要从事施工技术和管理工作。Email: 631984109@qq.com。

收稿日期: 2017-07-12

  修回日期: 2017-11-12

  网络出版日期: 2018-02-25

Study on Structural Design of Tunnel Portal at BridgeTunnel Connection Section Under Complex Terrain Conditions

  • WAN Junfeng ,
  • LI Dongsheng
Expand
  • (1. MengxiHuazhong Railway Co., Ltd., Beijing 100073, China; 2. China Railway Design Corporation, Tianjin 300142, China)

Received date: 2017-07-12

  Revised date: 2017-11-12

  Online published: 2018-02-25

摘要

蒙华铁路坪桥1号隧道进口洞顶基岩外凸、洞顶以下岩面高且直立、洞顶上部地形偏压高陡,地形条件极其复杂。营盘山大桥与坪桥1号隧道进口紧密相连,存在桥台与隧道洞门结构相互干扰以及边坡防护、隧道出洞和洞口场地布置等一系列难题,设计难度极大。为解决这些难题,通过对现场实际地形、地质情况进行研究,对比分析“整体式”与“分离式”桥隧相连结构的优缺点,提出桥台与隧道相结合的“整体式”桥隧相连结构方案;同时,针对地形偏压高陡,提出非对称结构设计方案,实现了隧道“零”仰坡出洞,解决了洞口边坡防护的难题;最后,提出架立临时贝雷梁的方案,解决了隧道出洞及洞口场地布置的难题。

本文引用格式

万俊峰 , 李冬生 . 复杂地形条件下桥隧相连隧道洞口结构设计研究[J]. 隧道建设, 2017 , 37(S2) : 169 -174 . DOI: 10.3973/j.issn.2096-4498.2017.S2.025

Abstract

Extremely complex terrains, i.e. rock bulge of tunnel roof, high and vertical rockface under tunnel roof, and asymmetricallypressured steep and high terrain on tunnel roof, are encountered during construction of Pingqiao #1 Tunnel portal on Menghua Railway; the Yingpanshan Bridge is connected to the tunnel portal; a series of problems, i.e. interaction between bridge abutment and tunnel portal structure, slope protection and tunnel portal breakthrough and layout of construction fields, exist in design. Hence, the terrain of construction site and geological conditions are investigated; comparing analyses are made for advantages and disadvantages of both integral mode and separation mode of bridgetunnel connection; the integral bridgetunnel connection mode is adopted; a design scheme for asymmetrical structure is proposed for asymmetricallypressured steep and high terrain to protect the slope; the problems of tunnel portal breakthrough and layout of construction fields have been solved by connecting constructed bridge with temporary bailey beam bridge.