Study of Measurement and Distribution Characteristics of Surrounding Rock Stress of Large Crosssectional Highspeed Railway Tunnel with Mechanized Construction
Received date: 2018-04-16
Revised date: 2018-07-08
Online published: 2018-09-04
于丽 , 王志龙 , 杨涅 . 机械化施工大断面高铁隧道围岩压力测试及分布特征研究[J]. 隧道建设, 2018 , 38(8) : 1303 -1310 . DOI: 10.3973/j.issn.2096-4498.2018.08.006
A large amount of field measurement on surrounding rock stress of tunnel group on Hubei Section of ZhengzhouWanzhou Highspeed Railway with mechanized construction are carried out to learn the variation laws and distribution characteristics of surrounding rock stress of large crosssectional highspeed railway tunnel with mechanized construction. And then the surrounding rock stress variation laws and distribution characteristics of surrounding rock stress in Grade Ⅳ and Grade Ⅴ deepburied conditions are analyzed and compared with standard loads based on measurement results. The study results show that: (1)The stabilizing time of surrounding rock stress starts on the 21st to the 27th day. (2)The measured surrounding rock stress is less than the calculated load of deepburied tunnel in related railway design codes. (3)Under the condition of Grade Ⅳ depth, the lateral pressure coefficient is 1.2-2.4 times that of standard load. (4)Under the condition of Grade Ⅴ depth, the lateral pressure coefficient is 0.86-1.43 times that of standard load.
/
| 〈 |
|
〉 |