Study of Mechanical Properties of Interaction between Surrounding Rock and Supporting Structure of ZhengzhouWanzhou Highspeed Railway Tunnel Constructed by Fullsection Method with Largescale Machinery
Received date: 2018-05-02
Revised date: 2018-06-29
Online published: 2018-09-04
为研究郑万高铁大型机械化配套全断面法施工围岩-支护结构相互作用力学特性,依托郑万高铁隧道现场实测数据,确定台阶法和大型机械化配套全断面法2种工法施工的围岩压力分布特征,并采用数值模拟的方法建立围岩-支护结构有限元模型,分析2种工法对围岩压力和结构内力的影响规律。研究结果表明: 1)台阶法多次施工扰动易导致支护结构和围岩之间产生空隙而发生脱空,大型机械化配套全断面法施工对围岩扰动次数少,初期支护快速封闭成环,可保证初期支护及围岩之间良好的密贴性; 2)在软弱围岩中,采用大型机械化配套全断面法施工比台阶法更有利于改善结构受力,减缓结构内部偏心受压的程度,能有效发挥拱形隧道结构承载力; 3)大型机械化配套全断面法在软弱围岩快速施工、控制支护结构变形、保证支护结构受力安全等方面具有综合优势。
于丽 , 蔡闽金 . 郑万高铁隧道大型机械化配套全断面法施工围岩-支护结构相互作用力学特性研究[J]. 隧道建设, 2018 , 38(8) : 1316 -1323 . DOI: 10.3973/j.issn.2096-4498.2018.08.008
The distribution characteristics of surrounding rock pressure of tunnels on ZhengzhouWanzhou Highspeed Railway constructed by bench method and fullsection method with largescale machinery are determined based on monitoring data. And then the finite element model of surrounding rocksupporting structure is established by numerical simulation to analyze the influence of the construction methods on surrounding rock pressure and internal force of the structure. The results show that: (1) The bench method would easily lead to the voids between supporting structures and surrounding rocks due to multiple construction times; while the fullsection method with largescale machinery disturbs surrounding rock little, and the primary support closure is rapid, which can ensure good tightness between primary support and surrounding rock. (2) In soft surrounding rock, the fullsection method with largescale machinery is superior to bench method in improving the structure stress, reducing the degree of eccentricity and compression inside the structure, and giving full play to the bearing capacity of the arch tunnel structure. (3) The fullsection method with largescale machinery has comprehensive advantages in rapid construction of weak surrounding rock, deformation control of supporting structure and safety guarantee of supporting structure.
/
| 〈 |
|
〉 |