施工技术

拱北隧道5台阶14部开挖施工组织方案分析

  • 熊昊翔 ,
  • 任辉 ,
  • 翁远林
展开
  • (1. 深中通道管理中心, 广东中山 528400; 2. 港珠澳大桥珠海连接线管理中心, 广东珠海 519060; 3. 中铁建港航局集团勘察设计院有限公司, 广东广州 510000)
熊昊翔(1989—),男,湖北石首人,2017年毕业于中山大学,地质工程专业,硕士,工程师,现从事高速公路建设管理工作。Email:270461922@qq.com。

收稿日期: 2018-06-21

  修回日期: 2018-08-04

  网络出版日期: 2019-03-05

Analysis of Construction Organization Scheme of Fivebench Fourteenstep Excavation Applied to Gongbei Tunnel

  • XIONG Haoxiang ,
  • REN Hui ,
  • WENG Yuanlin
Expand
  • (1. ShenZhong Link Administration Center, Zhongshan 528400, Guangdong, China; 2. Management Centre,  Zhuhai Link of Hong KongZhuhaiMacao Bridge, Zhuhai 519060, Guangdong, China; 3. CRCC Harbour & Channel Engineering Bureau Group Survey & Design Institute Co., Ltd., Guangzhou 510000, Guangdong, China)

Received date: 2018-06-21

  Revised date: 2018-08-04

  Online published: 2019-03-05

摘要

港珠澳大桥拱北隧道口岸暗挖段采用255 m曲线管幕+冻结法施工,采用5台阶14部开挖方法穿越富水软弱地层及拱北口岸敏感区域。为解决该工法下大断面开挖及多工序交叉作业施工的施工组织及安全问题,从现场管理角度出发介绍5台阶14部开挖法的施工方案,通过现场施工验证方案的可行性,并分析施工中存在的部分台阶断面划分、导洞施工顺序安排、工作面设置等方面存在的问题。据此,提出开挖方案和施工组织优化思路以及增设斜坡道的比选方案,监测结果表明: 施工组织调整及优化是切实可行的,能够确保拱北隧道按期顺利贯通。

本文引用格式

熊昊翔 , 任辉 , 翁远林 . 拱北隧道5台阶14部开挖施工组织方案分析[J]. 隧道建设, 2019 , 39(2) : 281 -286 . DOI: 10.3973/j.issn.2096-4498.2019.02.014

Abstract

The 255 mlong mined section of Gongbei Tunnel of Hong KongZhuhaiMacao Bridge, crosses waterrich weak stratum and sensitive area of Gongbei Port, is constructed by curved pipe roof + freezing method and fivebench and fourteenstep excavation method. In order to guarantee the smooth construction organization and construction safety, the detail of fivebench and fourteenstep excavation method is introduced from the perspective of site management; the feasibility of the scheme is verified by field construction; and the existing problems, such as crosssection division of some benches, construction sequence arrangement of pilot tunnel, working face arrangement, etc., are put forward. Finally, the idea of excavation scheme and construction organization optimization and the comparison and selection scheme of adding ramp are proposed, and the monitoring results show that: The construction organization adjustment and optimization are feasible, which can ensure the smooth completion of Gongbei Tunnel on schedule.