基金资助
中国铁路总公司科技研究开发计划(2016G004-A); 中铁隧道集团科技创新计划(隧研合2016-03,隧研合2018-06); 中铁建投科技创新计划课题((2016)-01-3); 深圳地铁集团科研课题(ZHDT-KY035/2017); 河南省自然科学基金(182300410197)
Shield Extension Technology of TBM Used in Parallel Adit of Gaoligongshan Tunnel
Received date: 2018-09-29
Revised date: 2019-03-11
Online published: 2020-03-11
李增 , 宋法亮 , 赵海雷 . 高黎贡山平导隧道TBM护盾延伸技术[J]. 隧道建设, 2019 , 39(5) : 876 -883 . DOI: 10.3973/j.issn.2096-4498.2019.05.020
Three serious jam accidents occurred to TBM when boring in parallel adit of Gaoligongshan Tunnel on DaliRuili Railway in fault and fractured zone. In order to reduce the construction risk, speed up the construction schedule and save the construction cost, the causes for cutterhead jam are analyzed, and the necessity and feasibility of shield extension are studied by means of investigation, engineering analogy and expert argumentation; and then, the shield extension scheme is developed, i.e. the space between shield and cutterhead is shorten from 360 mm to 50 mm. The practices show that under the proportion of grade Ⅳ and Ⅴ surrounding rocks reaching 67%, jamming accident does not occur when TBM continues to tunneling about 1 500 m, the tunneling efficiency is improved greatly and the effect of shield extension is remarkable.
Key words: Gaoligongshan Tunnel; parallel adit; TBM; broken ground; TBM jamming; shield extension
/
| 〈 |
|
〉 |