城际铁路大直径泥水盾构施工风险及对策——以佛莞城际铁路狮子洋隧道工程为例
收稿日期: 2019-03-19
修回日期: 2019-05-31
网络出版日期: 2019-07-02
Construction Risks and Countermeasures for Largediameter Slurry Shield Used in Shiziyang Tunnel on FoshanDongguan Intercity Railway
Received date: 2019-03-19
Revised date: 2019-05-31
Online published: 2019-07-02
王焰 . 城际铁路大直径泥水盾构施工风险及对策——以佛莞城际铁路狮子洋隧道工程为例[J]. 隧道建设, 2019 , 39(6) : 983 -988 . DOI: 10.3973/j.issn.2096-4498.2019.06.011
The cost and risk increase with shield diameter increase. Based on Shiziyang Tunnel on FoshanDongguan Intercity Railway, the risks existed in equipment type selection, longdistance deadend tunneling, uppersoft lowerhard strata and fault and fracture zone during largediameter slurry shield boring in complex strata with high water pressure and strong permeability are analyzed. The equipment adaptability is improved from the selection of atmospheric pressure cutterhead and slurry circulation system; the excavation parameter control method for excavation management and slurry management is determined; and construction countermeasures for uppersoft lowerhard strata and fault fracture zones are proposed to avoid significant geological risks and ensure construction safety of underwater largediameter shield.
/
| 〈 |
|
〉 |