Plan and Practice of Intelligent Construction System of SteelConcreteSteel Composite Immersed Tunnel of ShenzhenZhongshan Link(深中通道钢壳混凝土沉管隧道智能建造体系策划与实践)
收稿日期: 2019-12-28
网络出版日期: 2020-06-03
基金资助
广东省重点领域研发计划(2019B111105002)
Plan and Practice of Intelligent Construction System of SteelConcreteSteel Composite Immersed Tunnel of ShenzhenZhongshan Link
CHEN Weile , SONG Shenyou , JIN Wenliang , XIA Fengyong . Plan and Practice of Intelligent Construction System of SteelConcreteSteel Composite Immersed Tunnel of ShenzhenZhongshan Link(深中通道钢壳混凝土沉管隧道智能建造体系策划与实践)[J]. 隧道建设, 2020 , 40(4) : 465 -474 . DOI: 10.3973/j.issn.2096-4498.2020.04.001
Firstly, the main technical challenges, i.e. fabrication of steel tube, placement of selfcompaction concrete, quantitative check of compactness of selfcompaction concrete and longdistance floating transportation of steel tube, in steelconcretesteel composite immersed tunnels during industrialized and intelligent construction of ShenzhenZhongshan Link are analyzed. And then the construction philosophy of "standardization, industrialization, assembly, intellectualization, and refinement" is proposed, and the intelligent construction system for immersed tunnel of ShenzhenZhongshan Link is planned so as to ensure highquality construction, reduce the risk, and guarantee the time control in the whole construction. Finally, discussion is made from the aspects of intelligent fabrication of immersed steel tube element, intelligent placement of concrete, smart detection, intelligent installation of tubes and intelligent construction sites, etc.
/
| 〈 |
|
〉 |