• CSCD核心中文核心科技核心
  • RCCSE(A+)公路运输高质量期刊T1
  • Ei CompendexScopusWJCI
  • EBSCOPж(AJ)JST
二维码
施工技术

白城隧道工程大断面马蹄形盾构始发与接收技术

  • 章龙管 ,
  • 李志刚 ,
  • 谭江
展开
  • (1. 中铁工程服务有限公司, 四川 成都 610083; 2. 西南交通大学机械工程学院, 四川 成都 610031)
章龙管(1978—),男,安徽池州人,西南交通大学先进制造专业在读博士,高级工程师,现从事盾构与地下工程施工技术与管理工作。Email: zhanglongguan@cresc.cn。*通信作者: 谭江, E-mail: jiangtan820@163.com。

网络出版日期: 2020-07-29

Launching and Receiving Technology of Large Crosssection Horseshoeshaped Shield Used in Baicheng Tunnel

  • ZHANG Longguan ,
  • LI Zhigang ,
  • TAN Jiang
Expand
  • (1. China Railway Engineering Services Co., Ltd., Chengdu 610083, Sichuan, China; 2. School of Mechanical Engineering, Southwest Jiaotong University, Chengdu 610031, Sichuan, China)

Online published: 2020-07-29

摘要

为解决大断面马蹄形盾构始发与接收难点,以蒙华铁路白城隧道工程为依托,对大断面马蹄形盾构始发和接收施工关键技术进行总结。其关键技术包括: 1) 始发阶段采用加强明洞代替传统盾构反力架,可降低反力架的制作、拆除费用和减少始发负环管片用量,有效缩短主体施工时间,节约项目成本; 2)始发基座的底部均匀铺设豆砾石,可减少盾构进入原状土后始发导洞与管片背部间隙回填时间; 3)始发阶段创新地采用套拱钢架代替传统始发端墙结构,减少始发附属设施的工程量,缩短始发准备时间; 4)接收阶段基座与端墙相结合,降低盾构在软弱地层接收安全风险; 5)优化盾构始发和接收位置,使盾构施工和明洞主体作业面充分利用、互不干扰,实现较好的经济效益和安全效益。

本文引用格式

章龙管 , 李志刚 , 谭江 . 白城隧道工程大断面马蹄形盾构始发与接收技术[J]. 隧道建设, 2020 , 40(7) : 1041 -1048 . DOI: 10.3973/j.issn.2096-4498.2020.07.014

Abstract

The shield launching and receiving is one of difficulties for large crosssection horseshoeshaped shield tunnel construction. In this paper, the key construction technologies of shield launching and receiving of large crosssection horseshoeshaped shield used in Baicheng Tunnel on Menghua Railway are studied and summarized. The key technologies adopted include: (1) In the shield launching stage, the cost of reaction frame production and dismantling and the amount of original negative ring pipe can be reduced by replacing traditional shield reaction frames by strengthened open hole, which helps to shorten the construction time and save the cost. (2) The bottom of launching base is evenly laid with bean gravel to reduce the backfilling time of hollow between launching guide hole and pipe after the shield enters undisturbed soil. (3) In shield launching stage, the arch steel frame is innovatively adopted to replace the traditional launching endwall structure, which reduces the construction amount of launching ancillary facilities and shortens launching preparation time. (4) In receiving stage, the base is combined with the endwall to reduce the security risk of the shield machine receiving in the weak stratum. (5) The launching and receiving positions of shield are optimized to make full use of the main operation surface of shield tunneling and open tunnel without interfering with each other, which would realize better economic and safety benefits.
文章导航

/

〈 〉