为研究水下盾构隧道穿越圆砾地层时管片结构施工期间受力的影响因素,以常德沅江越江隧道为依托,选取东线隧道水头最高位置对应的管片环,采用连续动态测量,提取管片从拼装完成至盾构远离过程中管片结构内力和地层水压力,并提取盾构施工中同步注浆压力和盾构顶推力,与管片内力数据进行对比分析,得出施工过程中影响内力变化的因素。主要结论有: 1)同步注浆对管片内力的影响较为显著,且主要通过对地层水压力的影响来实现,其中,脱环后前3次注浆对管片内力影响最为显著; 2)顶推力对管片内力产生一定的影响,且主要通过对管片纵向受力的影响来实现,顶推力对内力产生负向影响; 3)管片受力稳定后,环向轴力稳定在3 700~5 000 kN,弯矩稳定在-200~200 kN·m,纵向轴力稳定在0~2 500 kN,整体呈现出轴力大、弯矩小的状态,管片健康程度较好。
To study the stressinfluencing factors of the
segments during shield tunneling through the round gravel stratum of Yuanjiang
River in Changde, China, the internal forces on the segment structure and
stratum water pressure at the segment ring with the highest waterhead on the
east line tunnel are obtained during segment assembling and shield passing
through. The synchronous grouting pressure and shield jacking force are also
extracted and are compared and contrasted with the internal forces on the
segment. The following conclusions are drawn from the study: (1) The
synchronous grouting significantly affects the internal force on the segment,
mainly by affecting the stratum water pressure. The first three groutings most
severely impacts the internal force of the segment after decoupling. (2) The
jacking force negatively affects the internal force on the segment, mainly in
the longitudinal direction. (3) When the segment force becomes stable, the
circumferential axial force and bending moment reach 3
700~5 000 kN and -200~200 kN·m,
respectively, and the longitudinal axial force reaches 0~2 500 kN, indicating a large axial force,
small bending moment, and good health of the segment.