(1. 中交四航工程研究院有限公司, 广东 广州 510230; 2. 南方海洋科学与工程广东省实验室(珠海), 广东 珠海 519000; 3. 中交四航局江门航通船业有限公司, 广东 江门 529145; 4. 中交四航局第二工程有限公司, 广东 广州 510230)
网络出版日期: 2021-10-01
基金资助
广东省重点领域研发计划项目(2019B111105002)
Design and Application of a Moving System with Wheel-Rail Trolley for Ultra-Large Components Used in ShenzhenZhongshan Link
(1. CCCC Fourth Harbor Engineering Institute Co., Ltd., Guangzhou 510230, Guangdong, China; 2. Southern Marine Science and Engineering Guangdong Laboratory (Zhuhai), Zhuhai 519000, Guangdong, China; 3. Jiangmen Hangtong Shipbuilding Co., Ltd. of CCCC Fourth Harbor Engineering Co., Ltd., Jiangmen 529145, Guangdong, China; 4. The Second Engineering Company of CCCC Fourth Harbor Engineering Co., Ltd., Guangzhou 510230, Guangdong, China)
Online published: 2021-10-01
董洪静 , 艾荣军 , 赵国臻 , 王晓东 . 深中通道工程超大型构件轮轨式台车移动系统设计与应用[J]. 隧道建设, 2021 , 41(9) : 1594 -1603 . DOI: 10.3973/j.issn.2096-4498.2021.09.019
Multiple problems will be encountered when the slip mode is adopted in the moving system of a large component. These problems include complex structure, fussy operation, difficult axis deviation control, low construction efficiency, and high operation cost. A moving system with a wheelrail trolley is designed and developed herein for a steelshell concreteimmersed tube prefabrication project in the ShenzhenZhongshan Link. A detailed analysis on this moving system is conducted from the aspects of the overall design, wheel diameter selection, bearing capacity review, roof design, and drive system design. A field test and a comparison of the construction efficiency and the economic benefits are conducted. The practical results show that the moving system with a wheelrail trolley has high construction efficiency and synchronization. Its axis deviation control also meets relevant specifications and design requirements, ensuring that ultralarge components with a weight exceeding 80 000 tons can be moved safely and efficiently.
/
| 〈 |
|
〉 |