为解决长大山岭隧道钻爆法机械化安全、快速、高质量施工所面临的技术问题,依托郑万铁路湖北段隧道工程,采用“科研先行、试验验证、推广应用”的工作方法,开展隧道大型机械化修建技术研究与现场试验。结合国内外调研情况及工程实践,得出如下结论: 1)隧道机械化修建方法是对传统方法的系统性改变; 2)Ⅳ、Ⅴ级围岩传统多台阶法、被动支护、围岩压力“分担比”理论与机械化大断面法不相适应; 3)机械化大断面法施工的核心要点是“快挖、快支、主动支、快封闭”; 4)隧道结构设计采用规范中基于松散压力的围岩压力计算方法与实际存在差异,可采用形变压力计算方法; 5)对于采用机械化大断面法施工的隧道,掌子面超前主动支护体系与洞身主动支护体系是确保隧道掌子面附近围岩稳定的关键。
To realize safe, rapid, and highlyefficient
mechanized construction of long mountainous railway tunnels using drilling and
blasting methods, a case study is conducted on a tunnel project of the Hubei
section of the ZhengzhouWanzhou railway. A working
method of "scientific research, test verification, popularization, and application,"
the exploration research, and field tests of largescale
mechanized construction technology of tunnels are performed. According to
investigations and engineering practice, some conclusions are drawn as follows:
(1) The mechanized construction method of tunnels is a systematic change based
on the traditional method. (2) The traditional multibench method, passive
support, and surrounding rock pressure sharing in Grades Ⅳ and Ⅴ surrounding rocks are unsuitable for
the large crosssection mechanized method. (3) The key
points of large crosssection mechanized construction
are fast excavation, fast support, active support, and fast closure. (4) The
tunnel structure design adopts the surrounding rock pressure calculation method
based on the standard loose pressure, which differs from the actual situation,
and can be designed according to the deformation pressure calculation method.
(5) For the tunnel constructed by the large crosssection
mechanized method, the advance active support system of the tunnel face and
tunnel body are the keys to the surrounding rock stability near the tunnel
face.