Deformation Characteristics of Tunnel Face and Corresponding Control Measures in FullyWeathered Red Sandstone Stratum
(1. China Railway Siyuan Survey and Design Croup Co., Ltd., Wuhan 430063, Hubei, China;
2. Key Laboratory of Transportation Tunnel Engineering of Ministry of Education, Southwest Jiaotong University,
Chengdu 610031, Sichuan, China; 3. School of Civil Engineering, Sichuan Agricultural University,
〖JP2〗Dujiangyan 611830, Sichuan, China; 4. Sichuan Higher Education Engineering Research Center for Disaster Prevention 〖JP〗
and Mitigation of Village Construction, Sichuan Agricultural University, Dujiangyan 611830, Sichuan, China)
Online published: 2022-08-23
王如磊, 王志杰, 徐海岩 . 全风化红砂岩地层隧道掌子面变形特征及控制技术研究[J]. 隧道建设, 2022 , 42(S1) : 301 -311 . DOI: 10.3973/j.issn.2096-4498.2022.S1.035
The failure of tunnel face stability often occurs during tunneling in fullyweathered red sandstone. Hence, a case study is conducted on the Yangcheng tunnel of HaolebaojiJi′an railway. Then a systematic study on the deformation characteristics and control measures of tunnel face in fullyweathered red sandstone stratum is conducted using various research methods such as field investigation, laboratory test, and numerical simulation. Research results reveal the following: (1) The extrusion displacement of tunnel face is mainly concentrated in the position of face height of 3~10 m, and the maximum extrusion displacement of tunnel face appears at the junction of upper and middle benches. (2) The crown settlement mainly occurs at about one time of the tunnel diameter in front of the excavated section and the tunnel face, which accounts for more than 40% in total deformation (with a maximum reaching 78.33%). (3) The change in the core soil extrusion curve in front of the tunnel face decreases rapidly first and then becomes slowly, which can be roughly divided into strong influence, weak influence, and no influence zones. The range of influence is 5.8~19.2 m. (4) The extrusion deformation of the tunnel face of Yangcheng tunnel can be effectively controlled by adopting advance horizontal jet grouting pile and threebench reserved core soil method. The two proposed methods can be applied under the premise of dewatering.
/
| 〈 |
|
〉 |