Application of Leveling and Positioning System for Gravel Bed of Excavator Used in ShenzhenZhongshan Link
(1. No.2 Engineering Company Ltd. of CCCC First Harbor Engineering Company Ltd., Qingdao 266071, Shandong, China; 2. Guangdong Highway Construction Co., Ltd., Guangzhou 510623, Guangdong, China)
Online published: 2022-08-23
韩战伟, 刘迪, 成益品 . 挖掘机定深系统在深中通道沉管隧道减载沉箱基床整平施工中的应用[J]. 隧道建设, 2022 , 42(S1) : 480 -485 . DOI: 10.3973/j.issn.2096-4498.2022.S1.056
In order to solve the safety risk problem of underwater human leveling caused by low tide level, high flow rate, and complex construction conditions at the top of E1 pipe section at the joint of the west artificial island of ShenzhenZhongshan link, automatic positioning measurement and control system of excavator equipped with GPS is developed to leveling caisson gravel foundation bed of load reduction. The position and attitude of the cab are calculated by GPS and biaxial inclinometer, and then the position and attitude of each swing arm and bucket can be calculated by the uniaxial inclinometer on each swing arm to guide the driver to carry out the construction leveling of the foundation bed. After the leveling of the gravel subgrade bed, the maximum value of elevation acceptance is +4.2 cm and the minimum value is -3.5 cm, meeting the design and construction requirements and improving the leveling accuracy of the gravel subgrade bed.
/
| 〈 |
|
〉 |