- CSCD核心中文核心科技核心
- RCCSE(A+)公路运输高质量期刊T1
- Ei CompendexScopusWJCI
- EBSCOPж(AJ)JST
(1. 山东科技大学资源学院, 山东 泰安 271000; 2. 山东科技大学安全与环境工程学院, 山东 青岛 266590; 3. 中铁十四局集团第一工程发展有限公司, 山东 日照 276800; 4. 山东科技大学山东省土木工程防灾减灾重点实验室, 山东 青岛 266590; 5. 山东科技大学矿山灾害预防控制-省部共建国家重点实验室培育基地, 山东 青岛 266510; 6. 山东科技大学煤矿充填开采国家工程实验室, 山东 泰安 271000)
网络出版日期: 2022-12-05
Application of Assembly Construction Technology for Large-Span Prefabricated Stations: a Case Study of Xixing Station on Changchun Metro Line 2, China
(1.School of Resources,Shandong University of Science and Technology,Tai′an 271000,Shandong,China;2.School of Safety and Environmental Engineering,Shandong University of Science and Technology,Qingdao 266590,Shandong,China;3.The First Engineering Development Co.,Ltd.,China Railway 14th Bureau Group,Rizhao 276800,Shandong,China;4.Shandong Provincial Key Laboratory of Disaster Prevention and Mitigation in Civil Engineering,Shandong University of Science and Technology, Qingdao 266590,Shandong,China;5.State Key Laboratory of Mine Disaster Prevention and Control,Shandong University of Science and Technology, Qingdao 266510,Shandong,China;6.National Engineering Laboratory of Coal Backfill Mining,Shandong University of Science and Technology,Tai′an 271000,Shandong,China)
Online published: 2022-12-05
关键词: 装配式车站; 预制构件; 拼装设备; 拼装技术
初明祥
,
彭传雄
,
胡忠经
,
张静静
,
何鑫
,
冯圆成
,
董嘉莲
,
王清标
.
大跨度装配式车站拼装施工技术研究与应用——以长春市地铁2号线西兴站为例
When constructing largespan prefabricated metro stations, the characteristics of precast components, such as their large weight and special shape, often affect their assembling accuracies and rapid positioning. Based on this fact, a case study is conducted on the Xixing station of the Changchun metro line 2, China. First, the prefabricated construction difficulties of the largespan underground station are investigated. Then, the requirements of the improved positioning assembly platform are described, after which the prefabricated construction technology is introduced in detail. Remarkably, this technology comprises the assembly method, assembly sequences, positioning process control, deviation correction control, foundation plane treatment technology, and mortise/groove grouting technology. Hence, the following conclusions are drawn from investigations: (1) The improved hydraulic 3D positioning assembly platform improves the assembly accuracy of an assembly
platform′s components. (2) Efficient, rapid, and accurate assembly is achieved using the developed prefabricated component assembly technology. (3) Accurate and efficient assembly of prefabricated components is realized by the established positioning and deviation correction control technologies./
| 〈 |
|
〉 |