海珠湾隧道是打通广州中心城区与南站枢纽快速连通的重要组成部分,具有接线路网复杂、超大直径、地质条件复杂及沿线结构物密集等难点,隧道总体设计难度大。首先,详细阐述隧道建设的意义,综合考虑总体规划、农田占用、征地拆迁和环境效应等因素,探索最优的平面线位,通过分析提出合理的技术指标;同时基于隧道建设条件与特点,制定沿线敏感结构物力学扰动评价指标和标准,开展隧道工法比选分析。然后,对推荐的盾构法进行横断面方案比选,并借助数值法评价不同断面方案诱发的既有结构力学响应,以支撑方案优选设计。最后,明确实施控制条件,进行推荐方案的平面、纵断面设计研究,并分析隧道建设关键技术;
针对海珠湾隧道建设特点,通过多因素综合比选,形成合理的工程总体设计方案。
Haizhu Bay tunnel is a crucial component for
establishing a fast connection between the central urban area and the south
station hub in Guangzhou. The general design is challenging due to its complex
connection network, superlarge diameter, complex geological
conditions, and dense structures along the line. The significance of the tunnel
construction is elaborated, and the optimal plane line is explored taking into
account overall plan, farmland occupation, land acquisition and demolition as
well as environmental effects, and then the reasonable technical indicators are
proposed. Meanwhile, the mechanical disturbance evaluation indicators and
standards for sensitive structures along the line are formulated based on the
conditions and characteristics of tunnel construction, and the tunnel
construction methods are analyzed and selected. The crosssection schemes for the recommended shield method are compared and
selected, and mechanical response of existing structures induced by different
section schemes are evaluated by using numerical method. Clarifying the control
conditions, the design of plane and longitudinal sections for the recommended
scheme as well as the key technologies are analyzed. In view of the
construction characteristics of Haizhu Bay tunnel, a reasonable general design
scheme has been formed through a comprehensive analysis of multiple factors.