施工技术

瓦斯隧道高应力低透煤层高低位钻场和水力冲孔相结合的消突技术——以昭通隧道为例

  • 周健 ,
  • 邱剑 ,
  • 曹泽琨 ,
  • 江明锋 ,
  • 吴华
展开
  • (1. 中铁隧道集团一处有限公司, 重庆 401120; 2. 太原理工大学安全与应急管理工程学院, 山西 太原 030024;3. 京昆高速铁路西昆有限公司, 北京 100000; 4. 中国中铁二院工程集团有限责任公司, 四川 成都 610000)
周健(1991—),男,湖北天门人,2014年毕业于湖北工业大学,土木工程专业,本科,工程师,主要从事瓦斯隧道揭煤及消突研究工作。 E-mail: 928141005@qq.com。*通信作者: 曹泽琨, E-mail: caozekun1342@link.tyut.edu.cn。

网络出版日期: 2025-12-20

Gas-Outburst Prevention Measures Combining High and Low Drilling Fields and Hydraulic Fracturing in Gas Tunnels With High-Stress and Low-Permeability Coal Seams: A Case Study of Zhaotong Tunnel

  • ZHOU Jian ,
  • QIU Jian ,
  • CAO Zekun ,
  • JIANG Mingfeng ,
  • WU Hua
Expand
  • (1. The First Engineering Co., Ltd. of China Railway Tunnel Group, Chongqing 401120, China; 2. College of Safety andEmergency Management Engineering, Taiyuan University of Technology, Taiyuan 030024, Shanxi, China; 3. Beijing-Kunming High-Speed Railway Xikun Co., Ltd., Beijing 100000, China; 4. China Railway Eryuan Engineering Group Co., Ltd., Chengdu 610000, Sichuan, China)

Online published: 2025-12-20

摘要

为解决昭通瓦斯隧道地应力高、煤层透气性低、瓦斯质量分数高、煤层松软等难题,通过理论计算对比分析平导洞与主洞分2次抽排瓦斯、平导洞与主洞一次性抽排瓦斯以及高低位钻场一次性抽排瓦斯3种隧道瓦斯抽排方案,择优选择高低位钻场瓦斯抽排方案,对昭通隧道M7—M9煤层开展现场瓦斯钻孔布局。在此基础上,选用高压水力冲孔技术进行煤层增透。现场研究表明: 1)相对于2种平导洞+主洞方案,高低位钻场方案的钻孔施工量分别减少约44%与19%,分别缩短施工周期0.5个月及3个月; 2)月累计抽排瓦斯纯量约20万m3,高位钻场消突效果达83%,低位钻场消突效果达85%,综合消突效果为84%。采用高低位钻场+水力冲孔相结合的瓦斯抽排技术,高效治理了昭通隧道瓦斯难题,确保了隧道顺利穿越高瓦斯煤层。

本文引用格式

周健 , 邱剑 , 曹泽琨 , 江明锋 , 吴华 . 瓦斯隧道高应力低透煤层高低位钻场和水力冲孔相结合的消突技术——以昭通隧道为例[J]. 隧道建设, 2025 , 45(S2) : 347 -354 . DOI: 10.3973/j.issn.2096-4498.2025.S2.031

Abstract

The Zhaotong gas tunnel faces various challenges, such as high ground stress, low permeability of coal seams, high gas content, and soft coal layers. Herein, three tunnel gas drainage schemes—two-phase gas drainage in the parallel guide tunnel and main tunnel, single-phase gas drainage in the parallel guide tunnel and main tunnel, and one-time gas drainage using high- and low-level drilling fields—are theoretially analyzed and compared. The optimal gas drainage scheme using high- and low-level drilling fields is selected, and a gas drilling hole layout for the Zhaotong tunnel′s M7-M9 coal seams is implemented. Based on this, high-pressure water jet fracturing technology is employed to enhance coal seam permeability. The field study shows that: (1) Compared to other two schemes, the drilling workload of the high and low-level drilling field scheme is reduced by approximately 44% and 19%, respectively, and the construction period is shortened by 0.5 and 3 months, respectively. (2) The monthly cumulative pure gas drainage volume is approximately 200 000 m3, the gas extraction efficiencies in the high- and low-level drilling fields are 83% and 85%, respectively, reaching a 84% comprehensive gas drainage efficiency. The scheme has successfully controlled the gas outburst volume and guaranteed the construction safety of the project. 