Replacement and Excavation of High Arch Dam in Weak Fractured Zone
介绍了锦屏一级水电站对高拱坝基础中f5断层、煌斑岩脉进行置换开挖的施工程序和方法,重点对软弱破碎带的开挖支护施工方法进行探讨,阐述安全监测指导不良地质地段施工的重要意义,总结适用于软弱破碎带开挖支护的施工方法,达到安全快速施工的目的。
何泽山,刘墅辉 . 水电站高拱坝软弱破碎带地层的置换加固技术[J]. 隧道建设, 2009 , 29(2) : 216 -221 . DOI: B
n this paper, the authors introduce the construction sequence and method of replacement excavation for high arch dam in lamprophyres of f5 fault in Jinping I Hydropower Station. Then, the authors mainly discuss the support and excavation method in weak fractured zone and indicate the significance of safety monitoring to construction in bad geological section. Finally, the authors sum up the reasonable construction method for support and excavation in weak fractured zone.
/
| 〈 |
|
〉 |