Protective Measures for Construction of Metro
Station Located above Existing Metro Line
Received date: 2007-07-10
Revised date: 2007-12-13
Online published: 2009-11-18
介绍了北京地铁五号线东单站暗挖段从既有地铁1#线区间上方跨过,为减少在既有地铁上方施工引起的卸载回弹,保证既有运营线的隆起变形控制在限制范围,采取的系列针对既有线的保护措施。
关键词: 暗挖车站既有线保护措施
翟云明 . 既有线上方地铁车站施工的保护措施[J]. 隧道建设, 2008 , 28(1) : 82 -84,92 . DOI: B
The mined section of Dongdan Metro station on line 5 of Beijing Metro crosses above existing line 1 of Beijing Metro. In order to reduce the unloadingresilience resulted from the construciton of Dongdan Metro station and to control the heaving deformation of the existing Metro line within the allowable range, a series of protective measures are taken. which are presented.
/
| 〈 |
|
〉 |