Discussions on Pullout Length and Powder Factor of Drill+blast Tunnel
爆破是隧道开挖的领头工序,开挖进度和成本是一对互动的因素。通过工程实例,就钻爆法隧道在限定单段装药量的情况下,对爆破掘进可取得的进尺进行验证;同时,在限定掘进进尺条件下,就隧道爆破合理的钻孔数量和装药量进行探讨。旨在提请业界重视对进尺和单耗的研究。
关键词: 钻爆法隧道掘进进尺炸药单耗
熊朝东 . 钻爆法隧道掘进进尺及岩石炸药单耗刍议[J]. 隧道建设, 2007 , 27(1) : 62 -64 . DOI: B
Blast is the leading sequence of tunnel excavation and progress and cost are a pair of interactive factors of tunneling. In this article, the achievable pullout length under restricted charge weight per delay is verified and the reasonable drill hole numbers and explosives to be charged for a certain pullout Length are also discussed. This article is aimed at drawing the attention of the technical persons in the field of tunneling to the importance of study on pullout length and powder factor.
/
| 〈 |
|
〉 |